Project Schedule
The Lynn Waterfront Master Plan process will take approximately 10-12 months to complete, depending on work flow. The work is divided into tasks as described below. The scheduled will be updated with meeting dates when appropriate.
Kick-Off Steering Committee Meeting |
June |
Site Analysis |
June - September |
Property Owner / Stakeholder Meeting |
July - October |
Analysis Presentation to the Community |
September 25, 2006 |
Alternatives Development |
October - December |
Alternatives Workshop with Community |
December 2, 2006 |
Preferred Plan Refinement |
January - April |
Economic/Fiscal Impact and Implementation |
March - June |
Draft Redevelopment Plan
Presentation to the Community |
May 12, 2007 |
Zoning Strategy, Chapter 91 Plan, and Harbor Plan |
June - August |
Presentation to Sub Committee of City Council |
August 7, 2007 |
Final Master Plan Presentation to City Council |
September 11, 2007 |
|