Lynn Waterfront Master Plan Web Site. Click to navigate to the home page.
Schedules

Project Schedule

The Lynn Waterfront Master Plan process will take approximately 10-12 months to complete, depending on work flow.  The work is divided into tasks as described below. The scheduled will be updated with meeting dates when appropriate.

Kick-Off Steering Committee Meeting June
Site Analysis June - September
Property Owner / Stakeholder Meeting July - October
Analysis Presentation to the Community September 25, 2006
Alternatives Development October - December
Alternatives Workshop with Community December 2, 2006
Preferred Plan Refinement January - April
Economic/Fiscal Impact and Implementation March - June
Draft Redevelopment Plan
Presentation to the Community
May 12, 2007
Zoning Strategy, Chapter 91 Plan, and Harbor Plan June - August
Presentation to Sub Committee of City Council August 7, 2007
Final Master Plan Presentation to City Council September 11, 2007

 









Photograph of a computer mouse on a desk calendar.
Home > Schedules