Schedule

Project Schedule

The Coconut Grove Waterfront Master Plan process listed below is an estimated schedule and may change due to scheduled meetings, availability of information, and community participation.

Initial Kick-Off Meeting May 3, 2005
Reconnaissance Trip 1 November 6-8, 2005
Walking Tour November 8, 2005
Reconnaissance Trip 2 December 14-16, 2005
Reconnaissance Trip 3 February 16, 2006
Analysis Presentation March 29, 2006
Development Plan Studies April-August
Design Alternatives Presentation December 11-12, 2006
Alternatives Refinement December - January
Refine Preferred Master Plan February - April
Draft Final Plan Presentation & Refinement April - May
Phasing and Implementation May
Documentation June
Final Presentation to City Council June




Please click here to see a list of all the public meetings to date.